JC Cost Activity Analysis Report window
Use this window to see an overview of your job costs for each job.
Report Type
From the drop-down, select the report type you want to view. You can choose:
• Detailed: this report displays detailed information about the estimated, actual, and cost variances for each code in each phase.
• Simplified: this report displays certain detailed information about the estimated, actual, and cost variances for each code in each phase.
• Condensed: this report displays estimated cost, actual cost, and the cost variance for each phase in the job.
• Summary: this report displays the estimated cost, actual cost, and the cost variance for each job.
Date Range
From the drop-down, select a
predefined period to run the report for.
Page break by Job Number
Select this check box if you want to begin each job on a new page.
Include completed jobs
Select this check box if you want to view completed jobs on the report. Jobs are complete when you select the Job Complete check box in the JC Job Maintenance window.
Skip jobs with zero WIP
Select this check box to omit jobs with no remaining WIP.
Cost Activity Date
Type the dates or use the drop-down to select the starting and ending dates for which you want to run the report.
Start and End: Job Number, Phase, Cost Code
The Start and End boxes allow you to define the range of items to include on the report. You can include a single item by entering the same value in both boxes. These default settings include all items that meet the remaining criteria set in the window. Type in the fields or use the Lookup to make your selections.
Cost Code Types to Include
Use these check boxes to select the type of Cost Codes you want to include on the report. Your options are All, Material, Subcontractor, General, and Process.