JC Work in Process Report window
Use this report to view all your cost codes, the cost activity date, actual cost, and remaining WIP for each phase of your jobs.
Report Type
From the drop-down, select the report type you want to view. You can choose:
• Detailed: this report shows you the cost information for each Cost Code in each phase of your jobs.
• Condensed: this report shows you the actual cost and remaining WIP for each Cost Code type in each phase of your jobs.
• Summary: this report displays the actual cost and remaining WIP for each job.
Date Range
From the drop-down, select a
predefined period to run the report for.
Page break by Job Number
Select this check box if you want to begin each job on a new page.
Include completed jobs
Select this check box if you want to view completed jobs on the report. Jobs are complete when you select the Job Complete check box in the JC Job Maintenance window.
Skip jobs with zero WIP
Select this check box to omit Cost Codes or jobs with no remaining WIP.
Start and End: Cost Activity Date
Type the dates or use the drop-down to select the starting and ending cost activity dates for which you want to run the report.
Start and End: Job Number, Phase, Cost Code
Type the job numbers, phases, and Cost Codes or use the Lookup to enter the ranges you want to include on the report. If you want to view one job, phase, or Cost Code, enter the same value in the Start and End fields. If you want to view all jobs, phases, or Cost Codes, leave the default of Start and End.
Cost Code Types to Include
Use these check boxes to select the type of Cost Codes you want to include on the report. Your options are All, Material, Subcontractor, General, and Process.